Action Items & Critical Dates

The path to opening: critical dates on the calendar, partner coordination with Pour Decisions, governance decisions still required, and recurring operating items.

Opening Timeline — Critical Dates

Each milestone depends on the one above. The Pour Decisions coordination items below must finish in parallel so the doors can actually open the week the CO arrives.

Date Milestone Why it matters
5/15 Fri Construction complete Site ready for inspections.
Wk 5/18 Mon City + health inspections Each re-inspection = +1–2 wks.
Late May / early Jun Certificate of Occupancy Releases $70K TI · legal to open.
6/1 Mon Rent commences $9,200/mo accrues whether open or not.
6/20 – 6/27 Sat Soft opening target Preferred window. Earlier feels rushed.
End of Jun Outer-limit opening Past this = burn beyond $180K target.
Next 7 Days
5/15 Fri
Construction completion + start of inspections cycle.
Rent Starts
6/1 Mon
$9,200/month — countdown begins regardless of opening status.
Opening Window
6/20 – 6/27
Outer limit: end of Jun. See timeline table above for full path.
Critical-path logic: hard READY deadline Fri 7/10 → inspections clear by 7/10 → TABC license lands by 7/31 → SOFT OPEN at White Linen Nights Sat 8/1 → GRAND OPEN Sat 8/8 → CO + $70K TI reimbursement releases shortly after. Every month of slippage past August adds $9,200 of pre-revenue rent burn.

Certificate of Occupancy — Minimum Requirements

CO is the gate. Everything below must be in place before the city will issue it. Anything not strictly required for CO can wait for the TI reimbursement to release ($70K) — see the Equipment Procurement Plan for the pre-TI vs post-TI breakdown.

Requirement Status Progress
Construction complete By 5/15 Fri
Final building inspection Wk 5/18 Mon
Final electrical inspection Pending
Final plumbing inspection Pending
Final mechanical / HVAC Pending
Final health inspection (incl. cooler interior wall) Pending
Hand sinks installed (blocking CO) Owner: Jason · Not Purchased
Fire / life safety Pending fire inspection
ADA compliance Verify at inspection
Business name on CO matches signage Verify on CO issuance
Strict CO-blockers vs. nice-to-have: rows tagged blocking CO (hand sinks, all "final inspection passed" lines, health, fire/life-safety) must be resolved before the city will issue. Everything else on this dashboard — POS, audio, video, security cameras, much of the equipment list, branded interior signage — can technically follow CO and the TI release. The Pour Decisions Coordination items above (A1 – A12) include both pre-CO items (hand sinks, cooler wall, exterior signage permit) and post-CO operational items (training, hiring, opening weekends).

Pour Decisions Coordination

Operational items running in parallel with the construction → CO path. Each item ties to a milestone on the timeline above.

# Item Date · Owner Status Progress
A1 Order beer draft system By mid-May
Jason
Order ASAP
A2 Espresso machine — leased directly by PD Corporate · PD Corp pays $1,100/mo · $0 PD Heights obligation Payments start 6/1 Mon
Jason (payments) · Rob + Vince (delivery)
Financed · ship pending
A3 Interior signage production By mid-Jun
Jason
Files received
A4 Exterior signage + permit kickoff Wk 5/11 Mon
Jason
Delivery this wk
A5 PD Nor Cal training trip By mid-Jun
Houston Partners
Dates TBD
A6 Houston hiring (Zoom interviews) By mid-Jun
Jason + Vince's team
Interviews starting
A7 Pour Decisions team Houston visit Wk 6/20 Sat
Vince
Dates pending
A8 Houston announcement + press On opening confirmation
Jason + Vince's team
Holding
A9 Video content for launch reels Rolling; launch wk
Jason + Vince
Initial shots requested
A10 Walk-in cooler interior wall Wk 5/18 Mon
Jason
Verify at inspection
A11 TABC beer & wine submittal ($3,000) Before opening wk
Ray + Rob + Boi
Not submitted
A12 Square POS hardware (4–5 boxes) ~5/15 Fri
Jason + Vince

Operational Status — Snapshot

Pour Decisions Coordination
12
A1 – A12 above
Operational Items Before Opening
3
Below — contractor, equipment, insurance
Already Decided / Closed
9
Lease, plans, builder, cooler wall, fridge panel, signage design, etc.

Required Before Opening

  1. 1
    Pay final contractor balance ($18,000) and close out punch list.

    Outstanding obligation. Required to reach Certificate of Occupancy. Not Paid

  2. 2
    Espresso machine — PD Corp direct lease.

    Espresso machine is now leased directly by PD Corporate at $1,100/mo. $0 PD Heights obligation — PD Corp covers the monthly lease. See A2.

  3. 3
    Sign off on insurance schedule pre- and post-TABC.

    General liability + property in place; add liquor liability and workers' comp once TABC is issued and payroll begins. Future

Items Already Closed

ItemStatus
Lease executed; security deposit + first month paid
Final architectural & engineering plans approved and paid
Permits, asbestos survey, & CO review fees paid
Builder selected; deposit paid ($24,000)
Walk-in cooler exterior wall replaced
Fridge panel sourced & installed (~$2,500)
Signage design locked (POUR DECISIONS white + Craft Coffee + Beer pink illumination)
Liquor (hard) license deferred — pursue post-opening; beer/wine via TABC
Cash box (not cash drawer) for POS
Bottom line: Contractor PAID OFF Monday 6/29. Project is fully funded ($146,789 contributed vs. $134,595 project cost = $12,194 working-capital cushion). Only $3,000 TABC license remains as a future obligation. Path to opening now runs through (a) equipment install + patio dress by 7/10, (b) inspections + TABC by 7/31, (c) staff orientation week of 7/27 (Breanna leading), (d) SOFT OPEN at White Linen Nights Sat 8/1, (e) GRAND OPEN Sat 8/8.

Governance & partnership decisions (ownership %, capital call rules, operator compensation, K-1 / bookkeeping classifications) are tracked on Partners & Ownership.

In-browser editing is live on this page. Click Edit mode (top-right) to toggle, then click any dashed-outline field to edit. Changes autosave on blur — green flash = saved, red flash = save failed.

Equipment Procurement Plan

Major equipment from the Pour Decisions spec. Plan: purchase the bulk of this list once the $70,000 TI reimbursement is issued post-CO. Lead-time-sensitive items (beer draft system) flagged in the table — to be ordered before TI lands to hit the August opening window. Espresso machine is leased directly by PD Corporate ($1,100/mo), so no PD Heights capex outlay required.

Item Cost Timing & Status Progress
Hand sinks (CO requirement) TBD Pre-TI · Owner: Jason
24-tap beer draft system TBD Pre-TI · 2–3 wk lead
Beer system parts (lines, regulators, faucets) TBD Pre-TI · 2–3 wk lead
Espresso machine — leased directly by PD Corporate $1,100/mo paid by PD Corp · $0 PD Heights Payments start 6/1 · No capex outlay needed
Beer drip tray (Micro-Matic, qty 2) ~$300–500 ea Post-TI
Drop-in ice bin (18″ × 36″) ~$200–400 Post-TI
Undercounter fridge (Avantco AU48R) ~$1,500–2,000 Post-TI
Bottle cooler (Perlick BC96 — optional alt) ~$3,000–4,000 Post-TI · under consideration
Walk-in cooler door / glass-door TBD Open — needs source
Main menu TVs (85″) ~$1,000–1,500 ea Post-TI
Beer menu TVs (55″ vertical, qty 2) ~$500–700 ea Post-TI
Fire Stick devices ~$50 ea Post-TI
Square POS hardware TBD
Security camera system TBD Post-TI
Audio system TBD Post-TI
Video install (mounts, cabling, switcher) TBD Post-TI
Walk-in fridge panel $2,500
Furniture — stools TBD Post-TI
Furniture — tables TBD Post-TI
Furniture — chairs TBD Post-TI
Prep tables (kitchen / bar stainless) TBD Post-TI
Kitchen inventory — small wares $10,905.24 Itemized on Capital
TI-dependency rule of thumb: if lead time + install time fits inside the window from TI release to soft opening (~2–3 weeks), the item can wait for TI. Anything longer must be pre-ordered. The two clear pre-orders are the beer draft system (2–3 wk on parts) and the espresso machine (custom paint extends the timeline). Pre-orders draw from existing cash + bridge capital; TI proceeds then reimburse / restore working capital after CO.